Solar PV design optimisation: getting more value from your project

Locogen’s solar design optimisation helps to identify the design that provides the best overall value for your project, taking into account more than just financial considerations.

Solar projects can reach EPC procurement with major design choices still unresolved, leaving developers and investors to assess contractor proposals without knowing whether the recommended layout will deliver the best financial outcome.

Our solar design optimisation solves this problem by identifying practical configurations that maximise project value before key commercial decisions are locked in.

Solar projects have a much wider range of design variables than wind and BESS projects. These can include PV table pitch, tilt angle, module and inverter selection, and the ratio between DC and AC capacity, among others. Many of these variables remain undetermined after planning consent has been secured, and might not become fixed until an Engineering, Procurement and Construction (EPC) contractor is appointed and the contract is signed.

Locogen’s design optimisation service addresses this gap by combining technical and financial modelling to test alternative configurations and identify robust, buildable designs within a project’s planning, grid and commercial constraints.

Here, we explain how and when our optimisation can add value to your project, and how the process works.


When does design optimisation add the most value?

There are two key stages in the project development lifecycle where design optimisation can be particularly useful.


During EPC procurement

During the EPC bidding process, contractors will typically propose their own design as part of their tender. But this raises an important question: is the EPC’s proposed design actually the one that delivers the best financial outcome for the project?

Our design optimisation process brings together technical and financial modelling to assess different possible configurations approach and identify the optimal layout for your specific site. This can then be included in the tender package, with EPC contractors asked to provide a price against the proposed design, while also giving them the opportunity to suggest improvements.

This provides a useful like-for-like basis for comparing different EPC tenders. It also means that any alternative design proposed by an EPC contractor is being compared against a design that is already close to an economic optimum.


During acquisition or a ready-to-build site

Design optimisation can also be useful when acquiring a solar project where the design has not yet been finalised.

In this case, we can benchmark the vendor’s proposed design against a range of alternative configurations. This helps establish how close the proposed design is to an economic optimum and, importantly, provides a better understanding of the potential value of the project.

How has solar PV design changed?

Previously, when Feed-in Tariffs (FiTs) and Renewables Obligation Certificates (ROCs) were available, the design philosophy was relatively straightforward. PV modules represented a significant proportion of project CAPEX (in some cases around 50%), so the focus was primarily on maximising the energy yield to be able to extract the most value out of the expensive PV modules while at the same time keeping within certain capacity due to the FiT and ROC project tiers. This generally meant higher tilt angles (around 20-25°), wider row spacing, low shading losses and a high Performance Ratio (PR).

However, the economics of solar have changed significantly since then. The end of the main subsidy regimes, combined with the reduction in PV module and installation costs over the last decade, has changed the way projects are designed. Today, the design question is less about how to generate the maximum amount of energy and more about how to get the best economic value from the available site. Lower PV module costs, together with site-specific constraints such as grid capacity, land availability and planning requirements, mean that there is no single design that works for every project.


Our approach to design optimisation

For our clients, we typically focus on minimising the Levelised Cost of Energy (LCOE) and finding the design that provides the best overall value for the project, considering more than just financial factors.

Diagram showing Locogen's solar design optimiastion process. Flow chart with the following 4 steps: 1. Define the financial parameters of the project, e.g. discount rates, energy price forecasts and operating costs. 2. Agree technical variables, such as the array tilt, row spacing, east-west layouts. 3. Run PVSyst simulations coupled with financial assumptions and then assess design possibilities. 4. Analyse results and identify best solutions within the project constraints.

We start by agreeing the key economic assumptions with the client, which can include discount rates, energy price forecasts, component pricing, operating costs, development costs, and other project-specific financial parameters. Having these agreed upfront ensures that the optimisation reflects the commercial assumptions used by the client.

We then agree which technical variables should be included in the optimisation. The range of variables can be tailored to suit the project and the level of design flexibility available.

Next, we use PVSyst simulations coupled with an external financial model to assess the energy yield and financial performance of each design. Depending on the size of the design space, a typical optimisation exercise can involve several hundred simulations and, in some cases, more than a thousand. Exploring the whole design space allows us to explore the trade-offs between different design options rather than relying on a single layout or a small number of scenarios.

Finally, the financial outputs are then filtered against any relevant project constraints, for example, specific table heights defined in the planning application. The result is a set of LCOE curves for the different scenarios considered. From these, we shortlist promising configurations that can then be reviewed with the client. The aim isn’t simply to find a theoretical “best” design. It is to identify practical designs that work within the project’s technical, planning and commercial constraints.


Getting the timing right

Solar PV design has become increasingly flexible, but that flexibility also creates more decisions and opportunities for inefficient designs. Carrying out design optimisation at the right point in the development or acquisition process can help ensure that key design decisions are made based on both technical performance and project economics.

If you’re acquiring a solar site or preparing to procure an EPC contractor for a solar PV project, get in touch to discuss how our design optimisation services could help you understand and maximise the value of your project.